andy brookes
Established Member
The build weekend was a long one, took friday off to build wall and get prepared for the assembly.....
Preps to the posts
Quick lay out of the main beams to make sure all the joints were correct
Wall Assembly
Saturday morning began with stripping the old roof off
By midday we had the new wall plates attached and all the beams and posts up
Then trusses
Saturday afternoon saw the final truss and loft boarding complete
Sunday was spent boarding the roof and getting some roofing sheet in place
Not a bad weekends work, lots done thanks to a couple of mates. Still obviously got lots to do. The roof is now waterproof. Need to stuff the walls with some insulation and a membrane on the uotside to keep the weather out until I can clad them.
Preps to the posts
Quick lay out of the main beams to make sure all the joints were correct
Wall Assembly
Saturday morning began with stripping the old roof off
By midday we had the new wall plates attached and all the beams and posts up
Then trusses
Saturday afternoon saw the final truss and loft boarding complete
Sunday was spent boarding the roof and getting some roofing sheet in place
Not a bad weekends work, lots done thanks to a couple of mates. Still obviously got lots to do. The roof is now waterproof. Need to stuff the walls with some insulation and a membrane on the uotside to keep the weather out until I can clad them.