The steel supports for over the openings were delayed and should have been with us two weeks ago; only arrived today on a typical wet Cheshire day. There are three supports, one over the two openings that can be used as double and single garage doors (I’m installing bifolds) and one over the large window. I’ve christened them the ‘goldie locks’ supports, as we have a thin support over the single, large support over the double and a ginormous support over the window opening. I’ve no idea why it’s such a large section beam, and the photo does not show it very well. But look at the size of it compared to the blocks.
The support beans are on gusseted steel pillars, which are bolted to the slab. The block work can now be completed up to wall plate height in the areas around the supports. The gable ends will be blocked up after the roof trusses have been installed. The brickies estimate a day of laying before the wall plates can go on ready for the roof a week on Monday.
The supports make me smile, when I’ve pulled out windows and doors and seen a bit of ‘scabby’ 4x3 of your lucky acting as a lintel or, in lots of cases the window frame is the lintel that have stood for hundreds of years.
View attachment 167906
View attachment 167907