Hi all, I'm finally progressing on my build after getting LOTS of help from this forum on how to approach my build.
I will first extend my current concrete base with a trench layout and will be following Mike's shed design (I'll be laying down concrete lintels and building from that)
The first step was to demolish the old shed and greenhouse, dig up the paving stones, and start digging the trench. The plan is to lay 150mm of MOT Type 1 and then 150mm of concrete with rebar. Will also install rebar dowels to connect old and new concrete. I'm glad I decided to break up these paving stones and not build directly on top as the mortar below it was approx 60mm deep and very crumbly. Probably would have been fine but I want this shed to last 20+ years so might as well try and do it properly
Trench digging finished. It's approx 300mm wide and 300mm deep
Laying sub base. Using MOT Type 1. I had to wheelbarrow all this through the house as it can only be dropped off at the front of the house.
That's all the progress for now. This has taken me over a month to do so far as I only have had a few hours spare here and there. I was hoping I'd get this built within a month but realistically it probably won't be finished till next summer, I've been putting off this part because I'm a little nervous about pouring concrete, but need to just crack on and give it a go.
I've already hit a snag in that I underestimated sub-base volume so I need another 1tonne bag delivered to bring up the sub-base level to 150mm and recompact it. Currently, it's sitting around 80-100mm thick.
Lesson learned #1 - I should have just gone with 100mm sub base and 100mm concrete base. Would have been more than enough for a workshop, cheaper, and less labour-intensive.
I will first extend my current concrete base with a trench layout and will be following Mike's shed design (I'll be laying down concrete lintels and building from that)
The first step was to demolish the old shed and greenhouse, dig up the paving stones, and start digging the trench. The plan is to lay 150mm of MOT Type 1 and then 150mm of concrete with rebar. Will also install rebar dowels to connect old and new concrete. I'm glad I decided to break up these paving stones and not build directly on top as the mortar below it was approx 60mm deep and very crumbly. Probably would have been fine but I want this shed to last 20+ years so might as well try and do it properly
Trench digging finished. It's approx 300mm wide and 300mm deep
Laying sub base. Using MOT Type 1. I had to wheelbarrow all this through the house as it can only be dropped off at the front of the house.
That's all the progress for now. This has taken me over a month to do so far as I only have had a few hours spare here and there. I was hoping I'd get this built within a month but realistically it probably won't be finished till next summer, I've been putting off this part because I'm a little nervous about pouring concrete, but need to just crack on and give it a go.
I've already hit a snag in that I underestimated sub-base volume so I need another 1tonne bag delivered to bring up the sub-base level to 150mm and recompact it. Currently, it's sitting around 80-100mm thick.
Lesson learned #1 - I should have just gone with 100mm sub base and 100mm concrete base. Would have been more than enough for a workshop, cheaper, and less labour-intensive.