On my previous post the existing shop required reroofing due to age and the new needed completion https://www.ukworkshop.co.uk/forums/viewtopic.php?t=23279&highlight=
Extensive rot was found in supporting timbers in two corners of the roof which turned a big day redecking into a exhausting day trying to close in and temp. waterproof.
the list of other jobs include laying floor, insulating cladding and lining the walls. A compleat rewire with additional lights. Forming a doorway to store/ dust extraction room. constructing a mitre saw stand, powertool stand, mobile assembly table (old dining table extendable) and a mobile stand for disc sander. also lots of rearranging of the layout etc.The roof was finally proofed by a local firm as this is a specialist job. So its just some painting thats required now.
Extensive rot was found in supporting timbers in two corners of the roof which turned a big day redecking into a exhausting day trying to close in and temp. waterproof.
the list of other jobs include laying floor, insulating cladding and lining the walls. A compleat rewire with additional lights. Forming a doorway to store/ dust extraction room. constructing a mitre saw stand, powertool stand, mobile assembly table (old dining table extendable) and a mobile stand for disc sander. also lots of rearranging of the layout etc.The roof was finally proofed by a local firm as this is a specialist job. So its just some painting thats required now.