@MikeK So you get three phase and neutral but what is the means of earthing used in Germany? In the Uk with domestic installations we get a lot of protected multiple earthing, PME systems where the supplier only gives live and neutral, the protective earth is derived from the neutral at the consumer end. In industrial applications we get three phase and neutral in the main cable and a separate earth wire is provided as well, using the zinc plated cable armour as the only earth is frowned upon as bad practice.
@Spectric, great question, and I hope these photos help to answer the question. As a rule, we avoid multiple earthing points.
We bought our house three years after it was built and the previous owner took hundreds of photos during the construction. I was having trouble locating the electrical cables, domestic water pipes, and radiator pipes. As soon as I examined the photos, I was able to trace almost all of the utilities throughout the house. All walls and floors are cast in place reinforced concrete, and the foundation is 50cm (500mm to the challenged) thick. The basement walls are 20cm (figure it out) thick and the upper floors are 15cm thick.
There is only one earthing point, and all other protective earth connections are derived from it. The earth point is a thick zinc plated copper strap that was bonded to the rebar before the concrete for the foundation was placed. When the form work was removed and the interior construction started, the copper strap was bonded to a copper bus attached to the wall at the service entry point. From the bus, all pipes in the immediate area were earthed and the PE cable from the distribution panel on the ground floor was terminated.
In this photo, you can see all of the utilities as they enter the basement below grade, as well as the copper earthing strap. I forgot to label it, but there is a thick gray cable in the upper right of the photo. This is the 3-phase 400V cable from the distribution panel on the ground floor. It will eventually be connected to the black 3-phase 400V input cable.
Here is a closeup of the copper bus with the plastic cover removed. This shows the copper strap and the PE cables after the insulation, screed, and floor tiles have been installed. This is the only earthing point inside the house. The exterior gutter and down spouts are earthed separately with ground rods and straps.
Here is another picture showing the current layout with the PE connections to the water and gas pipes. When we bought the house, we had a whole house water softener installed, so the main water line and sediment filter were rerouted. I also added an untreated water line to the outside of the house (the white pipe that drops and then goes to the right).